Friday, September 13, 2013

More Painting + Ceiling and Tile Install

Painting continued this week with the Customer Lounge. The paint contracter is priming the area where the TV will go. This will be the same charcoal as the accent stripe in the showroom.

The drop ceilings were installed. The tiles and lighting won't go in until all the tiling is done as to avoid dust from cutting tiles.




The walls in the bathrooms are painted and ready to go, so the next step was to install the tile.

The lighter tile went on the floor, with the accent tile going halfway up the wall.

Once it's dry, they'll grout it.

Lastly, they started preparing to tile the showroom floor. They put down product to level the floor for tiling. We'll have 16 tile installers coming on Monday, so it should go quickly.

We can't wait to see how the showroom floor turns out! It's going to be stunning.