Friday, April 19, 2013

Cutting Holes in the Wall & Other Updates

Here's what they've been up to next door the past few week.

If you recall, our new building is going to look like this -

But to get to that point, they need to take off the existing front to make way for the new one.


Here, they are taking up the concrete to make way for the new entry and arch.


Inside, the south side Showroom ramp was removed, and concrete poured to make the area level.

The stairway and ramp from the Customer Lounge to the Showroom was completed.

They worked on moving support poles from the middle of the Men's Bathroom to between the Men's and Women's Bathroom.


Back up in the Showroom, they took down the main wall to straighten it. The New Car Manager's Office will be right below the beam.

Outside, they made a really big hole in the shop wall. This new hole will be for the new exit door in the Service Drive-in.



Lots of progress has been made, but there's still lots to do before the Grand Opening this summer!